The beacon profile is a perforated metal rail in the form of the letter “T” or similarly fastened wooden blocks.
A plaster solution is applied to the profile, at a distance of about 35 centimeters from point to daughter. Then the rail is pressed against the wall at a distance of 10 centimeters from the corner. This must certainly be done absolutely evenly and strictly vertically — it is necessary to use the level. Reiki at the top and bottom are fixed on the wall with clusters or self -tapping screws, using the holes in them. After that, two thin cords are pulled, horizontally, between each two rails. The rest of the guides are installed already according to these cords. Nails or screws along with cords are removed only after the solution is completely dry.